PROJECT DESCRIPTION

Delta was part of the OAE Joint Venture team that designed the new south airfield Runway 10C-28C. In addition to the runway itself, extensive changes had to be made to airside infrastructure to accommodate this part of the airport expansion.

Delta provided both project coordination and design involved comprehensive civil design for pavements serving the proposed runway along, standalone pump station facility design and electrical lighting throughout.

Delta was responsible for the following major components of the runway addition:

ACCESS / SERVICE ROADS

Complete design for roads and parking lots:

  • Temporary North Service Road
  • FedEx Access Road
  • Division St re-routing
  • Airport Service Road
  • United Employee Parking Lot
  • Delta/NW Cargo Parking Lot

Design covered: alignments, plan and profile, grading, cross sections, pavement markings, MOT, fencing, signage, sidewalks, lot layout, storm sewer plan and profile, manholes, catch basins, and roadway / lot lighting.

SOUTH CARGO TUNNEL PUMP STATION & RETAINING WALL

Complete design of a 12’ diameter x 26’ deep, storm-water pumping station to dewater the South Cargo Tunnel using twin 50-HP, 2749 GPM pumps. Additional structures include an adjacent 9’x14′ rectangular valve vault and a 5’ diameter force main outfall structure. Cathodic protection was provide for the intake pipe and force main. Just south of the Cargo Tunnel at the intersection with the Airport Service Rd, Delta designed an 850’ long x 25’ high sheet pile retaining wall with tie-back anchorage which supports cargo parking lots.

UNITED CARGO APRON, FEDEX CARGO APRON AND TAXILANE ZH

Complete United Apron and partial FedEx Apron design which covered: demolition, removals, geometry; grading; cross sections; pavement jointing, elevation, and markings; storm sewers, underdrain, blast fencing, erosion control, and lighting. Delta also provided profile design for Taxilane ZH.

AIRSIDE LIGHTING DESIGN

  • Service roads and intersections
  • Obstruction lighting
  • FedEx Area, guard booth, temp. lot
  • Delta/NW cargo building parking lot
  • United & FedEx Apron

PROJECT AWARDS

  • ACEC Illinois 2014 Honor Award
  • ACEC National 2014 Honor Award
  • March of Dimes Award, 2014 Construction Project of the Year
  • ENR Midwest – 2014 Best Project Award in the category: Airports/Transit
  • Construction Industry Service Corporation, Infrastructure Project of the Year

CLIENT

Chicago Department of Aviation

PROJECT LOCATION

O’Hare International Airport

DELTA’S ROLE

Joint Venture Partner

SERVICES PROVIDED

Civil Engineering

Structural Engineering

Mechanical Engineering

Electrical Engineering

Plumbing Engineering

DESIGN SCHEDULE

2004 – 2011

CONSTRUCTION SCHEDULE

2009 – 2013

CONSTRUCTION VALUE

$641,000,000