HENRY & ROCK ISLAND COUNTIES

ADA SIDEWALK IMPROVEMENTS

PROJECT DESCRIPTION

Delta provided engineering design services for sidewalks and ADA ramps at over 150 quadrant locations in Henry and Rock Island counties. Design included preparation of final plans, quantities, time estimates and specifications.  Work was performed under Delta’s Phase I/II Various Projects contract.

The scope was split into three contracts with the following towns included: Andalusia, Andover, Alpha, Bishop Hill, Cambridge, Coal Valley, Edington, Milan, Osco, Reynolds, and Woodhull.

Final PS&E deliverables included:

  • Summary and schedule of quantities
  • Horizontal and vertical control plans
  • ADA and sidewalk ramp details
  • Pavement elevation plans
  • Incorporation of intersection signal plans prepared by IDOT

The project offered many challenges due to historic sites constraints, poor existing condition and close proximity of adjacent features. Delta provided additional quadrant specific design including:

  • Retaining wall for building entrance ramp
  • Drainage
  • Pipe culvert replacement and extension

PROJECT CHALLENGES

This project offered many challenges due to the historical site constraints, poor existing conditions, and close proximity of utilities and street fixtures. Delta’s team designed minimized ROW takes and were able to adjust or relocate utilities as needed. This included such design details as sidewalks at a new alignment and creating gradual transitions to facilities within the ROW.

CLIENT

Illinois Department of Transportation – District 2

PTB 181-008

Contracts: 64L12, 64L13, 64N39

PROJECT LOCATIONS

Various locations throughout

Henry & Rock Island Counties, IL

DELTA’S ROLE

Prime Firm

SERVICES PROVIDED

Civil Engineering

Structural Engineering

DESIGN SCHEDULE

08/2017 – 09/2019

CONSTRUCTION SCHEDULE

12/2021 – 12/2023

CONSTRUCTION VALUE

$3,980,990

PROJECT SORT LINKS

PROJECT PHOTOS

Before and after photos